Published on: Ethiopian Herald ( Sep 18, 2020 ) /Place of Bid Competitions:Addis Ababa
Remaining Time for Bid Submission
NOTICE OF INVITATION FOR BIDS
1.The Federal Democratic Republic of Ethiopia (FDRE) has allocated budget towards the cost of the following Road Construction Projects and intends to apply part of this budget to payments under these projects.
| Package V (5) | ||||||
| It. No. | Project Name | Estimated Length (Km) | Pavement Type | Project Duration | Contract Delivery | Procurement Type |
| 1 | Construction Works of Awash-Kulbi – Dire Dawa/ Harar Overlay Road Project; Contract I : Awash – Meiso (Km 0+000 – 70+500)(Re-Bid) | 70.5 | AC | 3.0 years | DBB | NCB |
| 2 | Awash – Kulbi – Dire Dawa/Harar Overlay Road Project; Contract II: Meiso – Hirna (Km 70+500 – 139+468) (Re-Bid) | 68.97 | AC | 3.0 years | DBB | NCB |
| 3 | Awash – Kulbi – Dire Dawa/Harar Overlay Road Project; Contract III: Hirna – Duse (Km 139+468 – 225+000) (Re-Bid) | 85.53 | AC | 3.0 years | DBB | NCB |
| 4 | Awash Kulbi Dire Dawa/Harar Overlay Road Project; Contract IV: Duse – Dengego – Harar & Dengego- Dire Dawa (KM225+000-290+864 & 0+000-19+541) (Re-Bid) | 85.41 | AC | 3.0 years | DBB | NCB |
| 5 | Construction Works of Addis – Gibe River Road Overlay Project; Lot II- Sebeta (Km 15+000) – Kore (Km 79+000) (Re-Bid) | 64.0 | AC | 3.0 years | DBB | NCB |
Note: – DBB = Design, Bid and Build; NCB = National Competitive Bidding; and AC = Asphalt Concrete
2. The Ethiopian Roads Authority now invites bidders to submit sealed bids for providing the necessary labor, material and equipment for construction works of the above road projects.
3. Interested bidders shall submit the following evidence:
a In the case of Ethiopian bidders, Certificate of Registration from Ministry of Construction with the relevant Categories as specified in item 4 of tables below renewed for 2012 EFY and other appropriate documentary evidences demonstrating the bidder’s compliance, which shall include:
i) Trading License renewed for 2012EFY;
ii) Tax Clearance Certificate, which states that the bidder can participate in any public tender, valid at bid submission date;
iii) VAT Registration Certificate; and
iv) Registration as Supplier in the list of the mandated public body, i.e. public Procurement and Property Administration Agency(PPPAA).
b. In case of bidders other than Ethiopians;
i) Business organization registration certificate or Trade License issued by the country of establishment.
ii) Tax Clearance Certificate issued from the Tax Authority (Inland Revenue Authority) which allows the bidder to participate in public tenders at the date of the deadline for bid submission If the foreign bidder already has on-going or completed projects in the Country; Ethiopia.
4. Bidding will be conducted through a National Competitive Bidding (NCB) procedures as specified on the tables above and is open to all eligible bidders as specified and defined in the Bidding Documents. The minimum Annual Construction Turnover, Cash Flow, General and Specific Construction Experience for each of the project is as shown below:
4.1 Qualification and Evaluation Criteria of Package V(5) Road Projects
4.1.1 Construction Works of Awash – Kulbi – Dire Dawa/Harar Overlay Road Project:
Contract I: Awash – Meiso (Km 0+000 – 70+500) (Re-Bid)
| It .No | Qualification criteria | Minimum Requirement | ||
| Local Bidders | Foreign Bidders | |||
| 1 | Annual Construction Turnover for the Last Five Years | ETB 135 Million (Peak) | ETB 337 Million (Average) | |
| The annual construction Turnover (ACT) requirement for a Joint Venture (JV) of Local and Foreign Firms is ETB 253 Million (Average). | ||||
| 2 | Liquid Asset/Cash Flow Requirement | ETB 42 Million | ETB 56 Million | |
| 3 | General Construction experience | 2 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | 5 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | |
| 4 | Specific Construction Project Experience | A Minimum of One (1) any type of Asphalt (DBST, TST or AC) Road Construction/Upgrading/ Rehabilitation/Overlay Project with a value of ETB 354 Million; OR A Minimum of Two (2) any type of Asphalt (DBST, TST or AC)Road Construction /Upgrading/Rehabilitation/Overlay projects each with a value of ETB 177 Million.In both cases, the experiences shall be within the last ten (10) years that has been successfully and substantially completed (70% Completed). | A Minimum of Two (2) Asphalt Concrete (AC) Road Construction / Upgrading / Rehabilitation / Overlay Projects each with a value of at least ETB 506 Million within the last ten (10) years that has been successfully and substantially completed (80% Completed). | |
| 5 | Grade | RC – 1 or GC – 1 | ||
Construction Works of Awash- Kulbi-Dire Dawa/Harar Overlay Road Project II:Meiso-Hirna(km 70+500-139+468)(Re-Bid)
| It .No | Qualification criteria | Minimum Requirement | ||
| Local Bidders | Foreign Bidders | |||
| 1 | Annual Construction Turnover for the Last Five Years | ETB 267 Million (Peak) | ETB 669 Million (Average) | |
| The annual construction Turnover (ACT) requirement for a Joint Venture (JV) of Local and Foreign Firms is ETB 502 Million (Average). | ||||
| 2 | Liquid Asset/Cash Flow Requirement | ETB 83 Million | ETB 111 Million | |
| 3 | General Construction experience | 2 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | 5 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | |
| 4 | Specific Construction Project Experience | A Minimum of One (1) any type of Asphalt (DBST, TST or AC) Road Construction/Upgrading/Rehabilitation/Overlay Project with a value of ETB 703 Million; OR A Minimum of Two (2) any type of Asphalt(DBST, TST or AC) Road Construction / Upgrading/Rehabilitation/Overlay projects each with a value of ETB 351 Million; ORA Minimum of Three (3) any type of asphalt (DBST, TST or AC)RoadConstruction / Upgrading / Rehabilitation projects each with a value of ETB 234 Million;In all cases, the experiences shall be within the last ten (10) years thathas been successfully and substantially completed (70% Completed). | A Minimum of Two Two (2) Asphalt Concrete (AC) Road Construction/Upgrading / Rehabilitation/Overlay Projects each with a value of at least ETB 1.004 Billion within the last ten (10) years that has been successfully and substantially completed (80% Completed). | |
| 5 | Grade | RC – 1 or GC – 1 | ||
4.13 Construction Works of Awash-Kulbi-Dire Dawa/Harar Overlay Road Project; Contract III:Hirna-Duse(km 139+468-225+000)(Re-Bid
| It .No | Qualification criteria | Minimum Requirement | ||
| Local Bidders | Foreign Bidders | |||
| 1 | Annual Construction Turnover for the Last Five Years | ETB 313 Million (Peak) | ETB 784 Million (Average) | |
| The annual construction Turnover (ACT) requirement for a Joint Venture (JV) of Local and Foreign Firms is ETB 588 Million (Average). | ||||
| 2 | Liquid Asset/Cash Flow Requirement | ETB 98 Million | ETB 130 Million | |
| 3 | General Construction experience | 2 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | 5 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | |
| 4 | Specific Construction Project Experience | A Minimum of One (1) any type of Asphalt (DBST, TST or AC) Road Construction /Upgrading / Rehabilitation/Overlay Project with a value of ETB 823 Million; OR A Minimum of Two (2) any type of Asphalt (DBST, TST or AC) Road Construction / Upgrading/ Rehabilitation/ Overlay projects each with a value of ETB 411 Million;ORA Minimum of Three (3) any type of asphalt (DBST, TST or AC)Road Construction / Upgrading / Rehabilitation projects each with a value of ETB 274 Million;In all cases, the experiences shall be within the last ten (10) years that has been successfully and substantially completed (70% Completed). | A Minimum of Two (2) Asphalt Concrete (AC) Road Construction /Upgrading / Rehabilitation/Overlay Projects each with a value of at least ETB 1.176 Billion within the last ten (10) years that has been successfully and substantially completed (80% Completed). | |
| 5 | Grade | RC – 1 or GC – 1 | ||
4.14 Construction Works of Awash-Kulbi-Dire Dawa/Harar Overlay Road Project
Contract IV: Duse-Dengego-Harar & Dengego-Dire Dawa (KM 225+000-290+864 & 0+000-19+541)(Re-Bid)
| It .No | Qualification criteria | Minimum Requirement | ||
| Local Bidders | Foreign Bidders | |||
| 1 | Annual Construction Turnover for the Last Five Years | ETB 327 Million (Peak) | ETB 818 Million (Average) | |
| The annual construction Turnover (ACT) requirement for a Joint Venture (JV) of Local and Foreign Firms is ETB 614 Million (Average). | ||||
| 2 | Liquid Asset/Cash Flow Requirement | ETB 102 Million | ETB 136 Million | |
| 3 | General Construction experience | 2 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | 5 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | |
| 4 | Specific Construction Project Experience | A Minimum of One (1) any type of Asphalt (DBST, TST or AC) Road Construction / Upgrading/Rehabilitation/Overlay Project with a value of ETB 859 Million; OR A Minimum of Two (2) any type of Asphalt (DBST, TST or AC) Road Construction / Upgrading/Rehabilitation/ Overlay projects each with a value of ETB 429 Million; OR A Minimum of Three (3) any type of asphalt (DBST, TST or AC)Road Construction / Upgrading / Rehabilitation projects each with a value of ETB 286 Million;In all cases, the experiences shall be within the last ten (10) years that has been successfully and substantially completed (70% Completed). | A Minimum of Two (2) Asphalt Concrete (AC)Road Construction / Upgrading/ Rehabilitation/ Overlay Projects each with a value of at least ETB 1.228 Billion within the last ten (10) years that has been successfully and substantially completed (80% Completed). | |
| 5 | Grade | RC – 1 or GC – 1 | ||
4.15 Construction Works of Addis- Gibe River Road Overlay Project : Lot II Sebeta (km 15+000)-Kore(km 79+000)(Re-Bid)
| It .No | Qualification criteria | Minimum Requirement | ||
| Local Bidders | Foreign Bidders | |||
| 1 | Annual Construction Turnover for the Last Five Years | ETB 326 Million (Peak) | ETB 815 Million (Average) | |
| The annual construction Turnover (ACT) requirement for a Joint Venture (JV) of Local and Foreign Firms is ETB 611 Million (Average). | ||||
| 2 | Liquid Asset/Cash Flow Requirement | ETB 101 Million | ETB 135 Million | |
| 3 | General Construction experience | 2 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | 5 Years firm experience under construction contracts in the role of prime Contractor, Joint Venture partner or Sub-Contractor. | |
| 4 | Specific Construction Project Experience | A Minimum of One (1) any type of Asphalt (DBST, TST or AC) Road Construction/Upgrading/Rehabilitation/Overlay Project with a value of ETB 856 Million; OR A Minimum of Two (2) any type of Asphalt (DBST, TST or AC) Road Construction / Upgrading/Rehabilitation/ Overlay projects each with a value of ETB 428 Million; OR A Minimum of Three (3) any type of asphalt (DBST, TST or AC)Road Construction / Upgrading / Rehabilitation projects each with a value of ETB 285 Million;In all cases, the experiences shall be within the last ten (10) years that has been successfully and substantially completed (70% Completed). | A Minimum of Two (2) Asphalt Concrete (AC) Road Construction / Upgrading / Rehabilitation/Overlay Projects each with a value of at least ETB 1.223 Billion within the last ten (10)years that has been successfully and substantially completed (80% Completed) | |
| 5 | Grade | RC – 1 or GC – 1 | ||
4. If a bidder is awarded and /or recommended for award of any two works Contracts by ERA six months prior to the bid submission date of the subject projects and until award of the subject projects, the qualification criteria for the construction turnover will be the aggregate of the criteria of the subject projects; and that of the awarded Contracts and/or those recommended to be awarded. A detailed qualification criterion is stated in the respective bidding documents.
5. Interested eligible bidders may obtain further information from and inspect the bidding documents at the address given below from 8:30 a.m. to 12:30 p.m. and 1:30 p.m. to 5:30p.m.local time from Monday to Thursday, and from8:30to11:30a.m.and1:30 p.m. to 5:30 p.m. local time on Friday.
A complete set of bidding documents prepared in English language may be purchased by interested bidders on the submission of a written application to the address below and a nonrefundable fee of ETB 1,000 or USD 40 for each project, effective as of September 21, 2020. The method of payment shall be in cash or direct deposit to ERA’s account in the Commercial Bank of Ethiopia – Sengatera Branch through Account No. 01715-33144600.
Address: Ethiopian Roads Authority, New Building Block B,
Engineering Procurement Directorate, 1st Floor, Office No. 102,
Tel: +251-11-833 29 81/515-30-15.5.
6. Bidders can apply for one or for all or for any number of projects from the above listed projects under the package and shall submit their bid separately for each project they are interested to apply for. However, bidders may be awarded on the projects under a package subjected to fulfilling of the Qualification Criteria for individual and multiple projects specified in the respective bidding documents based on the Employer’s best Economical advantage.
7. Bidders shall submit their Bids in two envelopes, the first envelop labeled as “Qualification Information and Bid Security” and the second envelope “Financial Bid”, separate sealed and the two envelopes sealed in on other outer envelope.
8. Evaluation is to be carried out in two stages, Qualification Information first and Financial Bids of qualified Bidders next.
9. Bids must be delivered to the address, time and date specified below. Each bid must be accompanied by a bid security of ETB 500,000.00 for each project in a format acceptable to the employer. Late bids will be rejected. One Original and five Copies of the bids have to be submitted. The Qualification information and Bid Security will be opened immediately after the submission deadline in the presence of bidders’ representatives who choose to attend, at the address below.
10.The value of total certified payments received in each year shall be adjusted for inflation of Birr value through multiplying by Cn/Co factor, where Cn is value of 1 US Dollar in Birr on the 28 day prior to bid submission date and Co is the value of 1 US Dollar in Birr computed using the selling exchange rate prevailing on the last date of the respective fiscal year.
11. For the Specific construction projects experience requirement, the Contract value of projects referenced by the bidder shall be adjusted to reflect the current purchasing power of Ethiopian Birr by multiplying with Cn/Co factor, where Cn is the current selling exchange rate of 1 US Dollar to Ethiopian Birr which is taken at the 28thdays prior to bid submission date and Co is the selling exchange rate of 1 US Dollar to Ethiopian Birr at the date of signing the Contract.
12.Bids must be delivered to the address below on or before November 05, 2020 at 2:30 P.M.
Director General
New Building, Block B, 2nd Floor, Conference Room Ethiopian
Roads Authority
Ras Abebe AregayStreet
P. O. Box 1770 Addis Ababa, Ethiopia Tel. +251-11-551 7170/79
Fax: +251-11-5514866
13. The Ethiopian Roads Authority reserves the right to acceptor reject any or all bids.
ETHIOPIAN ROADS AUTHORITY