3B+G+14 Tikur Abay Headquarter Building Project

Client: Tikur Abay Transport PLC

Consultant: MVR Consulting Group PLC 

Contractor: Amhara Building Works Construction Enterprise

Project Amount: 861,691,902.07 Including VAT

Contract Signature Date: Oct 12, 2022 GC

Site Handover Date: Oct 17, 2022 GC

Contractual Commencement Date: Nov 2, 2022 GC

Actual Commencement Date: Feb 6, 2023 GC

Duration of Project: 1,080 Days

Recent Pictures

List of Executed Tasks (From Nov 30, 2023 to Feb 22,2024 (84 Days)

  1. Columns, retaining shear walls, lift, stairs raised from 2nd and 1st  basement slab

  2. Ramp from 2nd basement to 1st basement and from 1st basement to ground floor

  3. 1st Basement Slab

  4. Ground Floor

  5. 1st floor slab preparation

Quality Tests

  1. 68 Cube taken and each sample passed the required quality requirement

Cost

Finance Demand of the Project

1) 22,222,903 Birr…Immediately

2) 86,169,190 Birr…Immediately

3) Gross: 113 Million/ Net : 74 Million…within 1month

4) 30 – 38 Million Birr Per Month for consecutive 5 months to achieve three floor per months…within 2 months

Time

Major Problems

Read more

Up-coming High 4-Risks

Risk-1

 

Read more

Completion of Construction

Article 23.1 Any lessee shall complete construction within the period specified in the lease contract following the provisions of sub article (2)

Article 23.2 The time limit for completion of construction shall be as follows:
c) up to 48 months for large construction projects

Article 23.5) Where a lessee fails to complete construction within the time limit specified under sub article (1) of this article, the lease contract shall be terminated and the appropriate body shall take back the land.

Article 23.7.a) upon ascertaining the conformity of the incomplete construction with the plan, transfer it, through open tender, to a person who can complete and use the building

Risk-2

 

Read more

Risk-3

 

Read more

Risk-4

 

Read more
Finally
The End!